SSE Arena – Chill Plant Replacement

Advanced Engineering Group delivered the replacement of an existing chiller plant at the SSE Arena, installing high-efficiency equipment and integrating new systems within a live operational venue.

  • Chiller Plant Replacement
  • Live Venue Installation
  • High-Efficiency Cooling
SSE Arena – Chill Plant Replacement

Project Overview

Advanced Engineering Group was appointed to deliver the replacement of an existing chiller plant at the SSE Arena, a major live events venue in the UK. The project formed part of a wider upgrade to enhance cooling efficiency, improve system reliability, and support long-term operational performance within a high-occupancy environment.

The works were carried out within a fully operational venue, requiring detailed planning and strict programme control to avoid disruption to scheduled events. Safe access, lifting operations, and controlled removal of the existing plant were critical to maintaining operational continuity while meeting all safety and compliance requirements.

Our team managed the safe decommissioning and removal of the existing chiller equipment before installing the new high-efficiency system. Mechanical works included pipework integration, alignment with existing building services infrastructure, and coordination with site stakeholders. All installations were completed in accordance with approved designs, manufacturer specifications, and industry standards, followed by comprehensive testing and commissioning to verify system integrity and performance.

Mechanical Services Delivered

  • Decommissioning and safe removal of existing chiller plant
  • Installation of new high-efficiency chiller equipment
  • Integration with existing mechanical and building services systems
  • Pipework modifications and mechanical connections
  • Coordinated lifting and plant positioning operations
  • Compliance with approved drawings and manufacturer specifications
  • System testing, commissioning, and performance verification
  • Live-site coordination within an operational venue
  • Final handover for full operational use

Project Outcome

The new chiller plant was successfully installed and commissioned, delivering improved cooling capacity, enhanced energy efficiency, and increased system reliability for the SSE Arena. The project was completed on programme with minimal disruption to venue operations, demonstrating Advanced Engineering Group’s ability to deliver complex mechanical plant upgrades within live, high-profile environments.