Project Overview
Advanced Engineering Group installed specialist cable containment for medium-voltage (MV) generator cabling as part of a data centre project in Dublin.
The works included the installation of heavy-duty cable ladder and cable tray to provide a supported route for the MV cables serving the generators. The team coordinated the containment routes with site requirements and aligned, levelled and secured the ladder and tray systems.
The double Unistrut support brackets were measured, fabricated and assembled in Advanced Engineering Group’s workshop before being transported to site. Preparing the brackets off-site reduced the amount of fabrication required on site.
Cable Containment Services Delivered
- Installation of heavy-duty cable ladder and cable tray for MV generator cabling
- Coordination of containment routes to suit site requirements
- Off-site fabrication and assembly of double Unistrut support brackets
- On-site installation and fixing of the brackets and associated support steelwork
- Alignment, levelling and securing of the cable containment systems
Project Outcome
The completed installation provided a secure, supported route for the MV generator cabling. The workshop-fabricated brackets and associated steelwork supported the cable ladder and tray in line with the project requirements.