Bentall Shopping Centre, London

Advanced Cabling Contractors completed an HV ring alteration at the Bentall Shopping Centre, installing 3-core 185mm² cable and executing jointing works within a controlled overnight shutdown window.

  • High Voltage Infrastructure
  • 11kV Substation Integration
  • Controlled Outage Works
Bentall Shopping Centre, London

Project Overview

Advanced Cabling Contractors were appointed to carry out alterations to the existing High Voltage (HV) ring at the Bentall Shopping Centre in London, as part of enabling works for a new cinema installation constructed on the roof of the building.

The scope required rerouting the HV ring between two 11kV substations along its original route to accommodate the new development. Due to the critical nature of the HV network supplying the shopping centre, the works required detailed pre-planning, strict sequencing, and execution within a tightly controlled outage window.

New HV cable sections were installed in advance of the scheduled shutdown. During the planned overnight outage, two HV jointing teams worked simultaneously to complete the required connections. Adequate curing time was allowed for the resin joints, followed by comprehensive testing and inspection to confirm integrity and continuity of the HV circuit prior to power restoration.

Cabling Services Delivered

  • Installation of 3-core 185mm² HV cable
  • Completion of 2 no. HV joints to integrate new cable sections into existing 11kV ring
  • Pre-installation of new cable sections prior to scheduled outage
  • Coordination of full HV network shutdown with centre management
  • Execution of works within overnight outage window
  • Resin joint curing and staged testing procedures
  • Full testing and inspection to verify circuit integrity
  • Restoration of supply ahead of shopping centre reopening

Project Outcome

The HV ring alteration was successfully completed within the planned outage window, ensuring uninterrupted operation of the shopping centre. All testing confirmed satisfactory results, and full power was restored prior to reopening. The project demonstrates Advanced Cabling Contractors’ expertise in delivering complex high-voltage infrastructure works within live commercial environments under strict programme constraints.